Marsabit Water Supply Project
Consultant: Saman-Korea Engineering Consultants Ltd (KECC) JV Professional Consultants as Sub-Consultant Contractor: Sinohydro Corporation Ltd Contract Value: KES 722,685,029.91 Commencement Date: 1ˢᵗ November 2018 Original Completion Date: 30ᵗʰ April 2020 1ˢᵗ EoT: 30ᵗʰ September 2021 2ⁿᵈ EoT: 31ˢᵗ March 2022 3ʳᵈ EoT: 31ˢᵗ July 2022 Scope of works Raise Bakuli Dam from 11.5m to 20m,…