Consultant: Saman-Korea Engineering Consultants Ltd (KECC) JV Professional Consultants as Sub-Consultant
Contractor: Sinohydro Corporation Ltd
Contract Value: KES 722,685,029.91
Commencement Date: 1ˢᵗ November 2018
Original Completion Date: 30ᵗʰ April 2020
1ˢᵗ EoT: 30ᵗʰ September 2021
2ⁿᵈ EoT: 31ˢᵗ March 2022
3ʳᵈ EoT: 31ˢᵗ July 2022
Scope of works
- Raise Bakuli Dam from 11.5m to 20m,
- Rising main – 7km
- Treatment works of 1,200 m³/day capacity
- New gravity main – 6km.
- 3 No. Storage Tanks 550m³
Progress during previous mission: 100%
Current progress: 100% complete
Completion Date: 8ᵗʰ November 2022
Disbursement: KES 414,335,156.69 (57.3%)
Challenges
- Damage of 1.4km water pipeline by road contractor
- Delayed delivery and installation of E&M equipment
- Delayed reservoir site clearance by the Contractor